Mission Critical Facilities

  • Sprint E|Solutions, 150,000 SF Web Hotel in Denver, Colorado
    This is a co-location and web hosting hotel for Sprint’s entry into that technology market. The building is a 150,000 SF facility with five 15,000 SF Customer Equipment Rooms designed for 160 watts per square foot of UPS power delivered to the Customer Room floor. The balance of space included 33,000 SF of Office and Support Space, 11,250 SF of UPS rooms, 8,440 SF of UPS battery rooms, 3,850 SF of POP rooms, 1,400 SF of 48 VDC batteries, and 32,000 SF of Support Area. The HVAC system is a mixture of chilled water and DX systems. The total building load was 5,500 tons of which 550 tons are DX systems and 4,940 tons of chilled water plant. A total of two 520 ton and eight 650 ton chillers will ultimately be installed to meet n+1 including redundancy on the mechanical system. A Plate and frame heat exchanger was installed under the first phase to provide chilled water for the building utilizing free cooling from the cooling towers and the system is laid out to incorporate 3 more heat exchangers for a total of 4080 ton of free cooling. State of the art building automation system with redundancy is utilized for complete monitoring and control of the facility. Monitoring is accomplished off site via the internet, along with 100% backup of all programs.

    Single preaction fire sprinkler systems and FM-200 systems are used in conjunction with VESDA detection system to provide fire safety for the complex.

    The building is fed by primary 15 kV power from the local Utility Company and will initially have two Owner provided 4,687 kVA transformers to step the voltage down to 480 volt power. Ultimately, the building will have five 4,687 KVA transformers to serve the total load. Initially, the building will have four 4,000 amps switchboards and ultimately will have nine 4,000 amp switchboards. Standby power will have two 2,000 kW 15 kV generators initially and will grow to ten 2,000 kW 15 kV generators ultimately. Power to the Customer Rooms will be via UPS modules. Each Customer Room will have two 750kVA modules paralleled together and designed for five 750 kVA modules.  A total of five systems will ultimately be used. The electrical system will provide 2N redundancy to the Customer Room floor.

  • Quintiles Lab Data Phase 1, Kansas City, Missouri                                Project consisted of mechanical, electrical, and plumbing design for installation of a redundant 300 KVA UPS module to an existing UPS system to support a 3500 SF Data Center.  Project included separate electrical and mechanical systems to serve the Data Center and Command Center.  Project was extremely fast paced, in which notice to proceed to start-up took only 4 months.  In conjunction with the Data Center, two different plans were evaluated to provide new primary 12.47KV service to the Data Center, as well as to improve the emergency standby generator system which currently serves the Data Center.  The study required close coordination with the end Users, Building Owner, Building Managers as well as the local Utility Company. 

  • Williams Communications, POP sites, Kansas City, Missouri
    One project included building out 12,000 square of backbone and co-locate area in an existing building. The project included connecting an existing 15kV substation to the exiting 15kV utility service and a new 1500 kVA transformer to serve the new 2000A 480V system. A new 1,250 kW standby generator was located in the basement, adjacent to the new 15kV substation. A 3000A DC battery plant supported the backbone area. The mechanical system included 10 computer room A/C units and two glycol dry-coolers for space conditioning. A pre-action dry-pipe sprinkler system was expanded into the new area.

    The second project included building out 25,000 square of backbone and co-locate area in an existing building. The project included a setting a new 2500 kVA transformer to serve the new 4000A 480V system. A new 2,000 kW standby generator was located outside adjacent to the new transformer. Provisions were made for the additional of another 2500 kVA transformer and 2000kW generator to support the 4000A Min-tie-main 480V-system. A 10,000A DC battery plant supported the backbone area. The mechanical system included the initial installation of sixteen 20-ton computer room A/C units and seven 50 glycol drycoolers for space conditioning, with provisions for this same quantity to be added at a later date. A pre-action dry-pipe sprinkler system was expanded into the new area.

  • AFN Communications, POP/Web Hosting Facilities in the Midwest and Northeast United States
    Multiple sites in the Northeast States of varying square footage ranging from 1250 SF to 15000 SF. Each site utilized computer room A/C equipment with DX condensing units or dry coolers with separate pump enclosure. HVAC system utilized N+1 redundant arrangement. Electrical systems were generally a 480V distribution to HVAC equipment, DC rectifier and step-down transformers for lighting and small appliance loads, however, some sites required medium voltage step-down transformers to achieve the 480V desired voltage. A standby generator set was installed to completely back up each site in the event of a power outage. DC battery plants varied in size and were based on 24 amps per rack with a 4-hour backup time. Design included layout of DC plant, ladder rack for DC power and fiber/copper cable distribution and telecommunications grounding to achieve 3 ohms. Most sites required a minimum of plumbing and fire protection generally utilized double-interlocked pre-action sprinkler systems initiated by smoke detectors and/or manual stations.

  • Blue Cross/Blue Shield Data Center, Kansas City, Missouri
    Project has a total of 39,500 SF of which 20,000 SF is 24" high raised floor area. HVAC system utilizes a central chilled water system with piping to units sitting on the raised floor. The chilled water loop provides the chilled water storage for cooling of main frames upon loss of power. Heat pumps are utilized to provide space conditioning in the office and support areas. Entire building is sprinkled and a double interlocked pre-action system is used in the raised floor area. Temperature controls use a DDC system to control all HVAC equipment. A separate monitoring system is used to monitor HVAC equipment in the computer room as well as power distribution units, UPS equipment and the main service equipment. The electric service consists of dual primary (15 kV) feeders with automatic throw-over equipment, a main-tie-main dual 480 volt switchgear with automatic throw-over, and auto transfer switches to accommodate future standby generators. In addition, the project includes two 500 kVA/400 kW parallel redundant UPS modules with 16 minutes of battery backup and three 415 Hz frequency converters paralleled to provide 415 Hz power to two 3090 mainframes. An emergency shutdown wiring scheme and signal reference grounding grid was utilized inside the computer room.

  • Jack Henry 4,000 SF Data Center, Union City, Tennessee
  • Jack Henry 4,000 SF Data Center, New Richmond, Wisconsin
  • Sprint BOCC, 7,500 SF Broadband Operating Control Center, Overland Park, Kansas
  • Sprint NOCC, 10,000 SF Network Operating Control Center, Overland Park, Kansas
  • Global One, 30,000 SF POP site, Santa Clara, California
  • Mobil Oil Credit Corporation, 13,000 SF, Lenexa, Kansas
  • ISS Computer Room, Marion Laboratories, 10,000 SF, Kansas City, Missouri
  • DST, Poindexter Bldg., 10,000 SF, Kansas City, Missouri

 


Company ProfileCareersGDS EmployeesHow To Find Us